On the cost estimator, what is meant by "production weeks"?

The question you're answering.
May 2, 2016
Login to flag as inappropriate
Does "production weeks" mean how many weeks the show will run, or the total rehearsal time plus production? We expect to begin rehearsals in late January and present the show on one weekend for 3 performances in April.
1 Answer

Staff Answer
May 2, 2016

For the cost estimator, "Production Weeks" refers to the length of the performance run. For instance, 3 performances taking place on the same weekend would be 1 production week. If the 3 performances were spead out over the course of 2 weekends, it would be 2 production weeks.